FREEDOM GENERATIONSchool“teach your children well”
ENاردو
School building under construction, 80% complete

In progress

Complete the School Building — 80% Complete

80% complete20% remains
Goal
Rs 3,383,520
Funded
Rs 0

Freedom Generation's building has been raised step by step since 2020. As of September 2026 the school building is 80% complete.

Already done — do not need funding:

  • School building structure completed
  • Classrooms constructed
  • Boundary wall completed
  • Basic plaster work completed
  • Main gate installed
  • Marble/tile flooring for hall and classrooms — finished this summer

What remains is everything that turns a sound structure into a finished school: complete internal wiring and lighting, ceiling fans and backup solar power, doors and windows with locks, staircase and washroom tiling, final paint inside and out, air coolers and exhaust fans, water tanks and filtration, furniture for classrooms and offices, fire safety and CCTV, and a structural engineer's report needed for registration.

Why this matters: without these installations the school cannot meet government registration requirements, ensure student safety, provide a comfortable learning environment, or open fully on schedule.

The full budget below was priced line by line in the Faisalabad market in 2026. We are raising Rs 3,383,520 for full completion with a 5kW solar system (12% contingency included). Essential completion without solar is Rs 2,543,520 — solar is the stretch goal that frees the school from unreliable grid power and heavy electricity bills.

Line-item budget — Faisalabad 2026

ItemQtyTotal (PKR)
A. Electrical Work
Internal copper wiring + labour7/29, 90m rolls, conduit1 lot150,000
Switch boards & fittingsAMSON pearl deluxe type3024,000
LED lights 12–13W3036,000
Ceiling fans AC-DC Inverter King Model2 per classroom + hall12156,000
Distribution board + breakers + install135,000
Backup — Solar 5kW hybridRecommended, or 3kW at Rs 450k1750,000
B. Doors & Windows
Classroom doors (solid)6150,000
Office doors250,000
Washroom PVC doorsPVC recommended426,000
Window glass + installation2080,000
Locks & handles sets1218,000
C. Flooring & Finishing
Flooring — DONEMarble/tile flooring finished summer 202600
Staircase finishing (tiles + edge)1 lot40,000
Washroom wall tiles + labour1 lot90,000
Final paint interior + exterior (45 gal + labour)ICI/Nippon @ Rs 4k avg + labour1 lot280,000
D. Ventilation & Cooling
Air coolers evaporative7175,000
Rooftop green shade sheetHeat protection500 sq ft60,000
Exhaust fans621,000
E. Plumbing & Water System
Water tanks (underground 1000G + roof 500G)1 lot85,000
Washroom fittings (taps, flush, etc.)460,000
Hand wash basins432,000
Drinking water facility (dispenser/cooler)125,000
Water filtration system + TDS meterHandwritten addition150,000
Dust remediation / sealing / cleaningHandwritten addition1 lot20,000
F. Furniture
Classroom shelving systemsHandwritten addition672,000
Teacher tables + chairs (9 sets)Table 12k + chair 5k9153,000
Whiteboards 4×6 ft756,000
Notice boards624,000
Principal desk135,000
Administrative tables240,000
Visitor chairs836,000
Filing cabinets236,000
G. Safety Requirements
Fire extinguishers430,000
First aid kits412,000
Emergency exit signage69,000
CCTV 4-cam + DVR165,000
H. Certification
Structural engineer report / certificationNeeded for registration140,000
Subtotal without solar2,271,000
Subtotal with 5kW solar3,021,000
Total without solar (incl. 12% contingency)2,543,520
Goal — with 5kW solar (incl. 12% contingency)3,383,520
Large hall interior, unfinished
Construction detail — wall and flooring work
What remains — roof and electrical detail